Thursday, December 28, 2006

Update and booth window installation





All of the skirting and architrave is now complete in both the main studio and the booth. Today, the angled, 750 x 750 sealed unit was installed in the booth (28mm deep). The angled pane was achieved by cutting down a 68mm piece of softwood from 50mm at one end down to 18mm at the other, thus forming two triangles which the pane could sit between. 5mm neoprene was also installed around the angled frame, both back and front to create mechanical separation between frame and pane. Prior to installing the architrave around the frame, all gaps were filled with decorator's caulk on both sides to reduce noise transmission as effectively as possible. (see picture).

Thursday, December 21, 2006

Update





A bit of an update on progress made .(apologies for poor picture quality as only had phone on me).


Both rooms are now painted and the laminate floor has been laid throughout. The Utility Room is complete and the new wine cooler fits just perfectly :)


The new fire doors arrived today too ready to be fitted on Saturday 30th December.


All that remains to be done in the studio before the fun wiring bits can commence (AV and mains) is for skirting and architraves to be fitted, window cills painted and the vocal booth window installed.

Monday, December 11, 2006

Photos




Here are a few images showing the new plaster in the studio and the new floor / paint etc. in the Utility. It is really difficult to get back far enough to show the Utility area, but that's not important any way - apart from the new wine cooler that is.

Utility update

Last weekend saw the painting of the utility room, its architrave and skirting installed and the laminate floor installed. Lighting in both rooms (Utility and Studio) is now on too. Photos to follow once I can find a camera :)

Friday, December 08, 2006

Plastering

Weds 6th December saw the plastering started and completed in one day. Photographs to follow.... It is hoped to get at least the Utility area painted and its floor laid this weekend.